Heat loss in metal wall construction.
|
Loose lug connection of a high voltage switch, photo courtesy of Flir Systems Inc.
|
Loose connection from a breaker to a fuse on both first and second phases, photo courtesy of Flir Systems Inc.
|
First phase fuse top clip is loose, photo courtesy of Flir Systems Inc.
|
First phase fuse clip and bolts are loose on a breaker, photo courtesy of Flir Systems Inc.
|
Third phase fuse top clip and lug for disconnect is defective, photo courtesy of Flir Systems Inc.
|
Third phase fuse and lug connection on a breaker is loose, photo courtesy of Flir Systems Inc.
|
Transformer bushing connection is loose internally, photo courtesy of Flir Systems Inc.
|
Refractory lining on a rotating kiln is defective, photo courtesy of Flir Systems Inc.
|
Defective 15 amp breaker found in a lighting panel.
|
Poor connection at the jaws of a switch on a high voltage tower.
|
Heat loss concrete insulated panel.
|
Loose fuse holder on a high voltage fuse, photo courtesy of Flir Systems Inc.
|
Wet fibreboard insulation panel on a flat roof, photo courtesy of Flir Systems Inc.
|
Wet insulation found adjacent to a roof drain.
|
Wet fibrous glass insulation panel found in a roof.
|
Electrical disconnect panel, thermal image of the 1st phase incoming lug connection found to be loose.
|
Evaluation of refractory lining in a process kiln furnace.
|
Evaluation of refractory lining for a process gas breaching.
|
Infrared image of defective refractory lining for process vessels and breaching.
|
Defective refractory lining for an incinerator.
|
Loose lug connection on a starter in an electrical panel.
|
Poor seals around doorway.
|
Defective knife blades in an electrical disconnect.
|
Loose fuse clips in an electrical panel.
|
Loose lug connection at top of an electrical breaker.
|
Defective elbow and bushing for a high voltage pad mount transformer.
|
Wet insulation found in a built up flat roof system.
|
Loose lug connection on a high voltage switch.
|
Defective high voltage switch. Poor closure at jaws of switch.
|
Heat loss around access doors on a gas breaching.
|
Refractory lining conditions for a process furnace and associated gas flue.
|
Heat loss for a boiler side wall casing.
|
Heat loss to due poor seals in walls.
|
Internal IR scan of a refinery process heater tubes.
|
Coke located on bottom tubes (light gray area) in a process refinery heater.
|
Heat loss door entrance seals.
|
Cold air infiltration at doors.
|
Wet insulation in a built up roof.
|
Wet insulation in flat roofs.
|
Refractory lining failure in a sulphur furnace.
|
Loose wire connection in an electrical panel.
|
Loose wire connections at fuse holders.
|
Loose termination of control wiring.
|
Missing insulation in walls.
|
Wet insulation in roof.
|
Heat loss at shipping door seals.
|
Heat loss from single pane windows in a building.
|
Heat loss from poor window seals.
|
Heat loss at roof line flashing.
|
Sample of missing insulation in plant wall.
|
Heat loss at window frames and seals.
|
Insulation missing in plant wall system.
|
Thermogram of wet insulation on a flat built up roof. Photo courtesy on Infraspection Institute.
|
Thermogram of wet insulation area on a roof adjacent to a soil vent. Photo courtesy of Flir Systems Inc.
|
Verification of moisture content in insulation during core test procedures and infrared scanning using a Delmhorst moisture probe.
|
Infrared photo of a loose jumper connection on a high voltage system, phost courtesy of Flir Systems Inc.
|